2021 NFWF Coastal Resiliency (Dune Enhancement) Project
Project Updates
October 5, 2021: NFWF Schedule/Project Update! The contractor will begin sand placement on the southern end of St. Joseph Peninsula beginning October 11, 2021. Sand will be placed between the Sunrise Sunset Condos (R-102) and the stumphole revetment. Due to limited beach width, the layout of the proposed vegetated islands has been adjusted. See the below figure for the updated layout. Based on the most recent aerials, homeowners located at 3857, 3849, 3791, and 3775 Cape San Blas Road are advised to remove any sand fencing seaward of their property prior to the start of the sand placement. See the circled properties in the figure below.
Sand placement is expected to be complete within a week or two and vegetation will be planted on the existing and constructed dunes following completion of sand placement.
June 28, 2021: NFWF Schedule/Project Update! Sand placement has been temporarily halted until September, when the remiander of the dune restoration project will resume. Sand placement activities have completed from the southern end of Rish Park to roughly the sunrise-sunset condos with the southern end of the Cape remaining. Native dune vegetation will be planted on the dune around the later part of July.
April 23, 2021: NFWF Schedule/Project Update! Construction progress had slowed in the last two weeks, however progress is still being made towards completion of the dune restoration project. The contractor will be finishing up the northern section of the project shortly and then will begin placing sand towards the south, starting at Aruba Drive once the north part of the project is complete. A detailed schedule is not available at this time, however the project will be finished by May 31. We greatly appreciate everyones patience to date.
March 24, 2021: NFWF Schedule/Project Update! The contractor is continuing to use Cape Palms Park access location for staging and sand stockpiling and the park remains closed to the public. The section between Aruba Dr. and R-93.5 is nearing completion and is expected to be finished by the end of the week. Sand is currently being placed along Haven Rd at R-94 and south of Summer House Ln. at R-92. The Contractor is expecting to finish the northern section (Aruba Dr. to Rish Park) within 2 weeks and then begin working at Aruba Drive and proceed south. Also, as a reminder if you haven't reached out to us and still have sand fencing on the beach in the shoreline areas between Aruba Drive and Scallop Cove convenience store area, now is the time to remove it to get the maximum amount of sand in front of your property.
March 16, 2021: NFWF Schedule/Project Update! The contractor is continuing to use Cape Palms Park access location for staging and sand stockpiling and the park remains closed to the public. Sand is currently being placed on the beach at 2 locations: 1) Around Tobago Dr and moving north, and 2) at Haven Rd near DEP R-Monument R-94 and moving south. The Contractor began grading and shaping the sand last week starting just north of Aruba Dr. and just south of Cape Palms Park. The contractor is anticipating completing the northern section (north of Aruba Drive to Rish Park) by next week. They will then begin working at Aruba Drive and further proceed south. Also, as a reminder if you have sand fencing on the beach in the shoreline areas between Aruba Drive and Scallop Cove conviencance store area, now is the time to remove it. to get the maximum amount of sand in front of your property.
NFWF Project - SAND FENCING REMINDER! Homeowners, please use the following images to determine if your sand fencing is within the limits of the dune restoration project. If so, please remove it as soon as possible so we can place sand and vegetation in front of your property! If you have questions or would like us to look at your specific property, please send us a message using the Contact Us form below. If you do not remove the sand fencing seaward of the existing dune, we can not place sand on your property. Sand fencing installed on or landward of the existing dunes will likely be okay and can remain. Boardwalks may not need to be removed, however it is recommended in order to get the most sand. The contractor will do their best to push sand up to and around the boardwalk, but may not be able to push sand under it.March 2, 2021: NFWF Project Update! The contractor is continuing to use the Cape Palms Park access location for staging and sand stockpiling. Work is currently being conducted in and around Tobago Drive, and moving north. The contractor will begin smoothing out the sand stock piles on the beach this week using a small bulldozer. The FAQ's have been tweaked to reflect the NFWF project. Also, as a reminder if you have sand fencing on the beach in the shoreline areas between Rish Park and Tobago drive, now is the time to remove it. to get the maximum amount of sand in front of your property.
March 1, 2021: Beacon Hill/St. Joe Beach Segment - FEMA Berm Dune Restoration Project Update! We have developed a seperate webpage for residents and homeowners located along the Beacon Hill and SJ Beach that will be impacted by the upcoming FEMA Berm (dune) project. The sidebar (to the right) contains the link to the site or alternatively you may click HERE.
February 26, 2021: Indian Peninsula Segment - FEMA Berm Dune Restoration Project Update! We have developed a seperate webpage for residents and homeowners located along Indian Peninsula that will be impacted by the upcoming FEMA Berm (dune) project. The sidebar (to the right) contains the link to the site or alternatively you may click HERE.
February 26, 2021: NFWF Dune Project Update! The project officially kicked off this past Wednesday, February 24, 2021 in the vicinity of R-97 (Aruba Drive). The contractor is currently utilizing the Cape Palms Park as the access point to the beach and is hauling stockpiled sand along the beach using offroad dump trucks. The contractor's current plan is to work north towards the north terminus of the project, which is the southern end of Billy J Rish park. Some questions have come in recently regarding, when is the contractor going to begin grading the sand? The answer is sometime next week. A small bulldozer will be utilized and the contractor will begin shaping the piles of sand located along the beach.
February 5, 2021: Schedule update! We are getting close to beginning construction of the NFWF Emergency Coastal Resilience Project. North Florida Construction, Inc. was awarded Bid No. 2021-05 and their tentative schedule will be to begin hauling and placing sand before the end of February. In preparation for the start of the project, please remove any boardwalks or sand fencing seaward of the existing dune in order to receive the maximum amount of sand. Boardwalks or sand fencing may be left in place, but may be buried or the contractor may elect not to fill if they are unable to access the template.
December 24, 2020: Gulf County is proud to announce that the National Fish and Wildlife Foundation (NFWF) Emergency Coastal Resiliency (Dune Enhancement) Project is now out for bid. The proposed project is located along the gulf front beach of St. Joseph Peninsula, Gulf County, Florida. The project consists of the construction of a dune enhancement project between DEP Monuments R-89.6 and R-105.5 extending from the Stumphole revetment to the north for 3.1 miles (16,254 feet), which is roughly the southern limits of Billy J Rish Park. The project consists of the placement of clean white beach compatible sand obtained from the Honeyville Sand Mine in Wewahitchka, Florida totaling approximately 78,930 cubic yards. In addition, the project includes the installation of multiple native dune vegetation species totaling approximately 619,126 plants along the project shoreline. Bidding documents and the advertisement for the bid can be found at the following link on Gulf County's Website (Search for Bid #2021-05) Gulf County Bids.
September, 2020: Gulf County was officially awarded $3.7 million in grant dollars to restore three miles of shoreline on St. Joseph Peninsula through sand and vegetation restoration. The proposed project will provide coastal resilience by increasing the stability and longevity of the beach sand and encouraging additional dune growth through trapping windblown sand, increasing storm protection by limiting the damaging effects of storm surge, and promoting wildlife protection and increasing habitat. Additional details regarding the award and others from the Emergency Coastal Resilience Fund can be found at the following link on NFWF's website: NFWF Emergency Coastal Resilience Fund - 2020 Grant Slate.
History and Background
Hurricanes Michael and Florence, Typhoon Yutu, and the coastal wildfires of 2018 caused more than $50 billion in damage and severely degraded a range of wildlife habitats. Congress provided funding under the Supplemental Appropriations Act of 2019 (P.L. 116-20), allowing grants to be awarded through a partnership between NFWF and NOAA. NFWF’s Emergency Coastal Resilience Fund was launched in August 2019, two months after Congress passed the emergency supplemental appropriations bill, to support natural and nature-based infrastructure that will help impacted communities and wildlife recover and be better prepared for future events.
Gulf County was officially awarded $3.7 million in grant dollars to restore three miles of shoreline on St. Joseph Peninsula through sand and vegetation restoration. The proposed project will provide coastal resilience by increasing the stability and longevity of the beach sand and encouraging additional dune growth through trapping windblown sand, increasing storm protection by limiting the damaging effects of storm surge, and promoting wildlife protection and increasing habitat. Additional details regarding the award and others from the Emergency Coastal Resilience Fund can be found at the following link on NFWF's website: NFWF Emergency Coastal Resilience Fund - 2020 Grant Slate.
Frequently Asked Questions
Project Construction
Construction Drawings For the 2021 NFWF Coastal Resiliency (Dune Enhancement) Project
Provided below are images of the plans that will be utilized for Construction. The plans provide details as to the proposed widths and profile shape along the proposed project. Please note the provided plans are being provided for review only.
Contact Us
If you have a specific question not addressed in the FAQ's, please feel free to send us a message. Typcial response times are between 24 and 48 hours during business hours.